Overall Energy Systems Testing
As well as performing the periodic Planned Maintenance of each part of the system, consideration should be given to testing the entire system on a regular basis.
An overall system test will involve putting the critical load at risk so careful arrangements and agreements must be made.
Mains Failure Test
Disconnect the mains supply to the protected power equipment for an extended period and check:
With no generator :
If a generator is installed:
1. the Automatic Mains Fail (AMF) equipment operates correctly
2. the generator auto-starts after the expected time
3. the generator output supply is correct and within acceptable UPS input limits.
4. the UPS accepts the generator supply
5. battery recharging takes place while the UPS is being supplied by the generator.
Mains Restoration Test
Following the Mains Failure Test, re-connect the mains supply to the protected power equipment and check:
Generator unavailable:
If the UPS is fitted with auto-restart facilities,
1. The system returns to normal operation automatically, otherwise all UPS modules can be re-started manually and the system restored to normal operation
2. All alarms can be reset.
If a generator is installed :
For further information regarding our range of uninterruptible power supplies, such as diesel generators please visit our website
You like what oocuz.com does? Give a tip here.
Any amount is very welcome:
Help oocuz grow-every amount is great.